BuyingAugust 12, 202613 min read

How long a van conversion takes, queue included

Build time is not the wait. Here is why every guide gives a different number, what stands between a deposit and a finished van, and what a delay costs.

Shops quote build time. Buyers hear delivery date. Those are different numbers, and the gap between them is where most of the frustration in this industry lives. Book a build in March expecting a summer of use, discover in August that your slot has not started, and you have lost a season you cannot get back. Here is the whole timeline, including the part nobody quotes.

How long it actually takes

Build time runs from four weeks for a budget conversion to fourteen months for full custom. Total wait from deposit to keys is commonly six to twenty months. The difference is the queue, and the queue is usually the larger half.

TierDesignQueueBuildDeposit to keys
Budget catalogueNone to 1 week1 to 3 months4 to 8 weeks2 to 5 months
Mid-range1 to 3 weeks3 to 8 months3 to 6 months6 to 14 months
Premium custom3 to 8 weeks6 to 12 months6 to 14 months12 to 26 months
Drawn from lead times published by shops in our directory. Queue lengths move with demand and with the season you book in.

Tier predicts wait more reliably than anything else, and it does so for a boring reason: a shop building its own layout for the fortieth time has the drawings, the cut list and the parts already sorted. Shops at the accessible end of the market can turn work around in weeks because there is nothing to design. Shops drawing each van from scratch cannot, and should not pretend otherwise.

Why every guide gives you a different number

Search this question and you will be told four to six months, three to twelve months, and twelve to eighteen months, all by shops that build vans for a living. They are not contradicting each other. They are measuring from different starting lines and none of them says which.

When the clock startsTypical figure quotedWhat it leaves out
Bench time on your van6 to 16 weeksDesign, queue, parts, handover. Most of the wait
Slot start to collection3 to 6 monthsThe queue, which is often longer than this figure
Deposit to collection6 to 20 monthsNothing. This is the number you plan around
First enquiry to collection12 to 26 monthsNothing, and it includes your own decision time
Four honest answers to the same question. Ask a shop which one it is quoting before you compare it to another shop.

This single ambiguity causes more disappointment than any genuine delay does. When you collect quotes, write the start point next to every figure, because a shop quoting eight weeks and a shop quoting nine months may be offering you the same delivery date. Asking which clock a number refers to belongs on the same list as everything else worth settling before you choose a shop.

Why the queue exists at all

The queue is not a sales tactic and it is not disorganisation. It is arithmetic.

A conversion shop with four bays and a four month build cycle completes roughly twelve vans a year. Take twenty deposits and you have created an eight month queue on the day you accept the last one, without anybody doing anything wrong. Every shop in this industry is small in a way buyers consistently underestimate.

For scale, the entire US factory van camper category is tiny. RVIA's monthly shipment survey recorded 909 van campers shipped across the whole country in May 2026, and 4,075 in the first five months of the year, against 138,160 RVs of all types. Custom conversion shops sit well below even that, and there are only so many of them: we hold published pricing for 46 US builders, and Colorado, the deepest state market in the country, has fifteen.

Two practical consequences follow. Booking in autumn rather than spring routinely halves the queue, because every buyer wants the van finished by June and shops fill summer slots first. And a shop with no queue at all is worth a question rather than a celebration, because in a market this small, availability usually means something.

It also explains why growth does not fix this. A shop cannot hire its way out of a queue quickly, because the constraint is rarely floor space. It is the one person who does the electrical properly, and that person takes a year to replace and longer to train. Shops that expand fastest are usually the ones that standardised their layouts first, which is the same reason their lead times are shorter.

What the build time is spent on

A mid-range conversion is not four months of continuous work on your van. It is roughly six to ten weeks of actual labour spread across a longer window, because materials arrive when they arrive, specialists are shared between projects, and your van sits in a bay next to three others.

  • Design and drawings, 2 to 6 weeks. Happens before your slot, and it is your speed rather than theirs. Slow decisions here push everything downstream by the same amount.
  • Strip, sound deadening, insulation, subfloor, 1 to 2 weeks. Fast, cheap in labour terms, and the part you never see again. Also the part that decides whether the van works in February.
  • Roof penetrations and electrical rough-in, 2 to 3 weeks. The specialist stage. Fan and solar cuts, window apertures, the wiring loom before anything covers it. Delays commonly start here because it is where the scarce skills are.
  • Cabinetry, 2 to 5 weeks. The longest single stage on a custom build, because it is manufactured rather than fitted. A shop with in-house CNC compresses this substantially.
  • Plumbing, appliances and finish, 2 to 3 weeks. Tanks, pumps, heater, fridge, upholstery, trim.
  • Commissioning, snagging and handover, 1 week. Everything run under load, faults found and fixed before you leave. Weak shops skip this and you find out in your first month.

Six weeks of work inside a four month build

Add those stages up and you get eight to twenty weeks of labour, against a build window that a shop will describe as three to six months. That gap is normal and it is worth understanding, because month two of a build is when most customers quietly start to panic.

Your van is not being ignored. It is waiting for a batch of parts, or for the one person who does electrical to finish the van in the next bay, or for a cabinet run to come off a machine that is currently cutting somebody else's. Shops interleave projects because the alternative is idle specialists, and idle specialists are what makes builds expensive.

What you should expect in return is visibility. A shop confident in its process sends photographs at named stages without being chased. A shop that goes quiet for six weeks and then asks for a progress payment has told you something about how the rest of it will go.

What makes it take longer

Four causes account for nearly every overrun, and you control two of them completely.

CauseTypical delayIn your control?
Slow decisions during design2 to 8 weeksYes, entirely
Change orders after build start1 to 6 weeks eachYes
Chassis availability1 to 6 monthsPartly, by buying used or supplying your own
Parts and appliance lead times2 to 10 weeksNo, but a good shop orders early
Late changes are the most expensive delay because completed work has to be undone before new work starts.

Change orders deserve the attention. Deciding in month three that you want a shower is not a scheduling adjustment, it is a redesign: the plumbing run moves, the electrical load changes, the cabinet already built no longer fits, and the water tank needs somewhere else to live. The cheapest moment to change your mind is before the drawings are signed, and the price of changing it later is set by a policy you should have read at the start.

Parts have their own clock

The stage list above assumes materials are on the shelf. Several key components are not, and their lead times run concurrently with the build rather than after it, which is why a shop that orders late loses weeks it can never recover.

ComponentTypical lead timeWhat it blocks if late
Lithium batteries and inverters2 to 4 weeksElectrical rough-in, so nearly everything after it
Windows and roof hatches3 to 6 weeksRoof and wall penetrations, which come early
Fridges, heaters, cooktops1 to 3 weeksCabinetry fit-out and final plumbing
Custom upholstery and cushions3 to 8 weeksHandover only, so it rarely blocks
The chassis itself1 to 6 monthsEverything. Nothing starts without a van
Lead times move with supply conditions. Ask when your shop orders long-lead items, not just whether it does.

The chassis is the one worth planning around. A factory order on a Sprinter, a Transit or a ProMaster in a specific wheelbase, roof height and drivetrain can take months to arrive, and a shop cannot begin work on a van that does not exist. Turning up with your own van removes the single longest external delay from the schedule.

What a delay actually costs you

Nobody writing about this attaches a number to a slipped date, which is why buyers accept vague completion targets that they would refuse if the cost were visible. Here is a three month overrun on a mid-range build, priced honestly.

  • Insurance already runningCover often starts at handover, but not always

    $240–$750

  • Storage or parkingIf the chassis is yours and sitting somewhere

    $0–$900

  • Loan or capital tied upDeposits paid against nothing usable

    $900–$3,000

  • Housing you meant to leaveThe largest line, and the one nobody counts

    $3,000–$7,500

  • Total, three month overrunBefore the missed season

    $4,140–$12k

A three month slip on a mid-range build. Substitute your own figures, but do the arithmetic before you accept a soft date.

The housing line is the one that catches people. Somebody who gave notice on a lease for a June handover and gets the van in September has paid three months of rent they had planned not to pay, which on its own can exceed the difference between two shops' quotes. That is the argument for a written completion date with a stated consequence, and it is a reasonable thing to ask for.

There is a softer cost too, and it is the one people regret. A van finished in October has missed the season it was bought for, which means the first real use is eight months after handover, by which time the snagging window has quietly closed on faults nobody found because nobody was living in it. Build slips do not just move the date, they move the shakedown into a period when the shop no longer has to care.

How to shorten the wait

  • Take a catalogue layout rather than a custom one. A shop building a layout it has built forty times moves faster, charges less and makes fewer mistakes. Custom is worth its premium when you have a real constraint, not by default.
  • Supply the chassis yourself. This removes the longest external delay outright, and buying used removes it immediately rather than partially.
  • Book in autumn. Summer slots fill first because everyone wants the van by June. The same shop can quote half the queue for a January start.
  • Sign off the drawings quickly, then stop changing them. The single largest lever you personally hold over the schedule.
  • Ask about cancellation slots. Queues shed customers constantly. A shop with a slot opening in six weeks will usually say so if asked directly, and almost never advertises it.
  • Consider a finished van from stock. Several shops keep completed builds. It is available now, the price is known, and it finances far more easily than a build that does not exist yet.
  • Split the work. Some shops do the electrical, plumbing and roof penetrations and hand the van back for you to finish. It shortens the shop stage substantially and takes the dangerous work off your hands.

Doing it yourself

A DIY build has no queue and no shop schedule, which makes it sound faster. It is almost never faster.

Hours per weekRealistic completionWho this is
5 to 1018 to 24 monthsWeekends only, full-time job, no workshop
8 to 1212 to 18 monthsMost first-time builders
20 or more6 to 12 monthsBetween jobs, or a partner working alongside
Full time3 to 6 monthsRare, and usually somebody with a trade background
A complete build runs 300 to 800 hours of hands-on work. First-time builders consistently land at the upper end.

The reason first attempts run long is not laziness, it is that three stages take far longer than anybody's estimate. Electrical typically runs two to four times the planned hours for somebody learning it, plumbing two to three times, and cabinetmaking three to five times, because square cuts in a vehicle with no square surfaces are genuinely difficult. Doubling your own estimate is not pessimism, it is the observed pattern, and the honest comparison between doing it yourself and paying a shop has to price those hours rather than ignore them.

What to agree before you pay

Three dates in writing, not one. The date your slot starts, the target completion date, and the date your deposit stops being refundable.

That third one is what shops are least likely to volunteer and most likely to matter. It frequently falls when the queue begins rather than when the build does, which can be six months before anybody touches your van and long before you have seen a single piece of evidence that the shop can deliver.

Ask for one more thing while you are at it: what happens if the target date slips by more than a month. A shop with an answer has thought about it. A shop without one will improvise, and the improvisation will not favour you. Both questions cost nothing to ask and they sort shops faster than any amount of reading about what different tiers of build cost.

Key takeaways

  • Build time is 4 weeks to 14 months. Deposit to keys is commonly 6 to 20 months.
  • Ask which clock a quoted figure refers to. Bench time, slot start and deposit date give wildly different answers to the same question.
  • The queue is arithmetic, not a tactic. A four-bay shop finishes about twelve vans a year.
  • A mid-range build contains only 6 to 10 weeks of labour spread across a longer window. That is normal.
  • Long-lead parts run concurrently with the build. Ask when your shop orders them, not whether.
  • Booking in autumn rather than spring routinely halves the queue.
  • A three month overrun can cost $4,000 to $12,000 once housing and tied-up capital are counted.
  • Get three dates in writing, including when your deposit stops being refundable.

Common questions

How long does a van conversion take?

Build time runs from four weeks for a budget conversion to fourteen months for full custom. Total wait from deposit to collection is commonly six to twenty months, because the queue before your slot begins is usually longer than the build itself. Always ask a shop whether a quoted figure means bench time, slot start to collection, or deposit to collection.

Why do different builders quote such different timelines?

Because they start the clock in different places and rarely say so. Bench time on your van is six to sixteen weeks, slot start to collection is three to six months, and deposit to collection is six to twenty months. All three are honest answers to the same question, which is why two quotes that look far apart can mean the same delivery date.

Why is there a waiting list for van conversions?

Good shops are small and can only build a handful of vans at once, so demand queues. A shop with four bays and a four month build cycle completes roughly twelve vans a year, which means twenty deposits creates an eight month queue immediately. For scale, RVIA recorded 909 van campers shipped across the entire United States in May 2026.

How long does a DIY van conversion take?

Commonly 300 to 800 hours of hands-on work, which is twelve to eighteen months for somebody putting in eight to twelve hours a week. Full-time work brings it to three to six months but that is rare. Electrical, plumbing and cabinetmaking all run two to five times longer than first-time builders plan for.

Can I speed up my van conversion?

Take a catalogue layout instead of custom, supply the chassis yourself, book an autumn slot rather than a spring one, sign off drawings quickly and stop changing them, and ask directly about cancellation slots. Late change orders are the largest self-inflicted delay because completed work has to be undone before new work starts.

How long does the design stage take?

One to three weeks on a semi-custom build and three to eight weeks on a genuinely bespoke one, and it happens before your build slot starts. It moves at your speed rather than the shop's, so arriving with your priorities settled rather than working them out during the process is the cheapest time you will ever save.

Do van builders build multiple vans at once?

Yes, almost always. Your van shares the shop with several others, which is why a build described as four months contains only six to ten weeks of actual labour on your vehicle. Shops interleave projects so specialists are never idle, and idle specialists are what makes builds expensive. It is normal rather than neglect.

What delays a van conversion the most?

Change orders after the build has started, because completed work has to be undone first. Chassis availability causes the longest external delay at one to six months, and appliance and window lead times run two to ten weeks. Slow decisions during design are the delay buyers cause themselves most often.

When is the best time of year to book a van conversion?

Autumn and winter. Every buyer wants the van finished by June, so shops fill summer slots first and quote their longest queues in spring. Booking a January or February start routinely halves the wait at the same shop, for the same build, at the same price.

What does a delayed van conversion cost me?

A three month overrun on a mid-range build commonly runs $4,000 to $12,000 once you count insurance already running, storage, capital tied up in deposits and the housing you had planned to leave. The housing line is usually the largest and almost nobody budgets for it. That is the argument for a written completion date rather than a soft target.

Should I buy a finished van instead of waiting?

It is worth considering if timing matters more than specification. Several builders keep completed vans in stock, and a finished conversion is available immediately, carries a known price and finances far more easily than a build that does not exist yet. The trade-off is that you take the layout somebody else chose.